The 5,000-Seat Church — A Sanctuary of Faith & Community

Our church will be a beacon for the Christian community in Sargodha, Pakistan: a welcoming, modern, and accessible space designed for worship, fellowship, and growth. With room for 5,000 worshippers across two levels (about 110,000 sq ft), every detail serves comfort, safety, and dignity

Vision of the Church

We dream of building a sanctuary for our Christian brothers and sisters in Pakistan. A place where families can pray freely, celebrate their faith, and raise their children with dignity. This church will not just be walls, but a home of hope, love, and light for generations to come.

Spaces & Layout

This project is not just about one big hall — it’s about creating spaces for every part of community life. The main floor will host worship for thousands, while the upper floor will give children, youth, and families dedicated places for learning, prayer, and fellowship.

Comfort & Safety

We want to build a place where families can worship in comfort and safety. With modern cooling systems, fire protection, and safe design, this church will provide peace of mind along with spiritual peace.

 

Capacity & Design

Our vision is to design every corner with care. Comfortable seats, safe aisles, and a layout that welcomes everyone — young, old, and those with special needs. This will be a church built with inclusivity at its heart.

Worship Technology

We believe in using technology to make worship stronger. The church will have big screens, a clear sound system, and lighting that brings prayers and songs alive. Teaching and youth programs will also have modern equipment to support learning.

Cost Summary

This is a big project, but together it is possible. Every gift, small or large, brings us closer to making this dream real. The total cost is about $4.5 million, and we are trusting God and His people to provide.

Bill of Quantities (BoQ) — 5,000-Seat Church

Sargodha, Pakistan (All prices in USD)

Project Snapshot

  • Capacity: 5,000 seats (padded, carpeted cement step seating)
  • Building Area: ~110,000 sq ft total — Level 1 (auditorium/support) + Level 2 (classrooms, offices, kids & youth)
  • Seat Geometry: 18″ rise × 24″ tread (aisles use smaller code-compliant risers with handrails & step lights)
  • Selections: Air-cooled chillers + AHUs • LED wall • Partial HVAC backup on generator
  • Wheelchair Seating: 45 positions + 45 companion seats (Front 14 • Mid 18 • Rear 13)

 

Selected Systems & Scope

HVAC (Air-cooled Chillers + AHUs)

  • 4 × 120-ton modular air-cooled chillers (N+1; ~360 tons peak on three, one standby)
  • AHUs: 2 × ~60,000 CFM (auditorium) + 3 × ~15,000 CFM (L1 support) + 2 × ~12,000 CFM (Level 2)
  • Primary/secondary chilled-water loop with VFD pumps; low-noise distribution; basic BMS

Fire & Life Safety

  • Wet-pipe sprinklers throughout (assembly densities); addressable fire alarm + voice evac
  • Emergency lighting & exit signs; photo luminescent aisle/step markings
  • Fire pump & onsite tank (as required by pressure/flow)

Accessibility

  • 45 wheelchair positions + 45 companion seats; dispersed front/mid/rear
  • 2 passenger elevators (on generator) + stage/platform lift; 1:12 ramps with 60″ landings
  • Platforms: 22 pods of 2 + 1 single (typical platform 8′ × 4′ clear)

Plumbing & Restrooms

  • Western-style seated toilets only (no squat pans). Floor-mounted/wall-hung WCs with seats; accessible-height WCs (17–19″)
  • Accessible: 1 wheelchair-accessible stall in each men’s & women’s room + 1 ambulatory-accessible stall in each; 1 family/accessible single-user toilet per floor
  • Men’s: WCs + urinals with privacy screens; Women’s: WCs; sensor flush valves; solid-core partitions; baby changing in family rooms
  • Finishes/MEP: Ceramic tile floors & wainscot; exhaust & make-up air; sensor faucets; mixing valves; floor drains; hose bibs

A/V (LED Wall Option)

  • LED wall: ~10 m × 5 m (P3.9), processors, rigging; Dante/AV-over-IP backbone
  • Audio: L/R arrays (~12+12) + 8–12 subs, fills; 64-ch digital console; stage boxes; DSP
  • Lighting: 24–32 LED washes + 8–12 profiles; DMX control; dimmable house lights
  • Education/Office A/V (Level 2): 6 teaching display/projection kits + youth hall PA; paging

Electrical & Partial HVAC Backup

  • Generator ~600 kW, sound-attenuated; 1600 A ATS; clean power panels for audio
  • Backed loads: 1 chiller module (~120 tons), 1 auditorium AHU (reduced CFM), CHW pumps, OA/relief fans, both passenger elevators, FOH A/V racks, LED wall, egress/house lighting (select), fire alarm
  • UPS for control/FOH; surge protection

Seating Finishes & Safety Details

  • Commercial loop/rib carpet + 8–12 mm underlay on treads; direct-glue in aisles
  • Contrasting aluminium/rubber stair nosings at every row; continuous aisle handrails
  • Low-profile step lights along aisles

Second Floor Program

  • Adult Sunday School: ~10 classrooms @ ~600 sq ft each (~6,000 sq ft)
  • Kids’ Church: ~5,000 sq ft large room + ~2,000 sq ft breakout
  • Youth Group Hall: ~4,000 sq ft + storage
  • Offices/Meeting: ~2,500 sq ft (offices, conference, reception)
  • Circulation/MEP/Toilets: ~4,500 sq ft
  • Level 2 Total: ~20,000 sq ft (overall building ~110,000 sq ft)

Bill of Quantities (Condensed)

Major Item Qty/Size Notes
Air-Cooled Chillers 4 × 120 tons VFD condenser fans; BACnet gateway
Air Handling Units 2 × 60k + 3 × 15k + 2 × 12k CFM MERV-13 filtration; low-noise
CHW Pumps (VFD) 2 duty + 1 standby / loop Primary/secondary; DP sensors
Ductwork & Diffusers Allowance Low-velocity supply; lined returns
BMS Points ~300–400 I/O Scheduling, alarms, CO₂ DCV (non-assembly)
Sprinkler System Full coverage (~110k sq ft) Valves, risers, test/drain, heads
Fire Alarm/Voice ~320 devices Panels, amps, speakers/strobes, pulls
Elevators + Platform Lift 2 + 1 Passenger elevators on generator
Restrooms (Men/Women/Family) L1 + L2 groups Accessible & ambulatory stalls included; fixtures/partitions/exhaust
Wheelchair Platforms 22 pods of 2 + 1 single Total 45 positions + 45 companions
LED Wall ~10 m × 5 m Processors, rigging, 5% spares
Audio System Arrays + subs + console 64-ch console, stageboxes, DSP
Stage/House Lighting 32–44 fixtures LED washes/profiles; DMX control
Education/Office A/V 6 kits + youth PA Displays/projectors; paging
Generator & ATS ~600 kW; 1600 A ATS Selective transfer to backed loads
Clean Power & UPS As specified Isolated ground; surge protection; FOH UPS
Seating Finishes ~35–40k sq ft Carpet + underlay on treads; nosings; step lights; rails

Cost of Summary

Work Package Allowance (USD)
Structure/Envelope/Interiors (incl. Level 2 & seating finishes) $1,700,000
HVAC (air-cooled chillers + AHUs + BMS) $700,000
Fire & Life Safety (sprinklers + alarm/voice) $320,000
Accessibility (2 elevators, lift, ramps, seating positions) $200,000
A/V (LED wall + audio + lighting + infra) $370,000
Electrical & Backup (generator, ATS, clean power, UPS) $260,000
IT/Security/Low Voltage (incl. paging) $80,000
Plumbing – Men’s/Women’s/Family Restrooms (fixtures, piping, finishes) $180,000
Direct Subtotal $3,810,000
Design/Permitting/Surveys (~8% of direct) $305,000
Contingency (~10% of direct) $381,000
Projected Total (All-In) $4,496,000